All,
Here is a recap of the current status of the project.
Progress since yesterday:
- Continued CPR regulator support implementation work. Dmitry estimates this work is between 30% and 50% complete.
Work In Progress:
- Complete the CPR regulator work today or early tomorrow.
Planned Work:
- CBF requires special handling in the CPR driver, so implement that
- Utilize CBF for CPUfreq scaling
- Consider utilizing CPR driver for the GPU regulator powerup
- Finalize extra corner cases in the CPR driver
Other:
If the CPR regulator support work does not complete today, Dmitry will postpone that work, generate and test a 5.15 kernel with the CPU clock fixes and CBF clock support in it for delivery to Sightline, then resume the CPR regulator
work.
Budget burn: Yesterday, Dmitry spent 3.25 hours on the project, equating to .4 person days. That leaves 6.6 person-days left in the engineering budget. I spent .25 hours, meaning 28% of the 1 day of PM time has been consumed. We still feel
we are on-track to deliver the project outcomes as expected and within the current budget.
If you have any questions, please feel free to reach out to me at any time.