From: Paul Neuhardt <paul.neuhardt@linaro.org>
Sent: Monday, July 25, 2022 12:19 PM
To: sightlineapplications@lists.linaro.org
Subject: [Sightlineapplications] Project Status EOD Sunday, 24 July 2022

 

All,

 

As was noted in the last update, Dmitry worked Friday and over the weekend to catch up with work not completed last week.

 

Over Friday and the weekend, he spent 10.5 hours and accomplished:

   - Complete a fix for the OPP tables for CPU frequencies

   - Worked on implementing the CPUs LDO and APM voltage regulators. 

 

Budget burn:

  - As of the start of the day today, we have consumed 54.75 of the 80 engineering hours available, leaving 25.25 hours remaining. I have consumed a total of 4.50 of the 8 project management hours. 

 

At this point, I would recommend we have a conversation about prioritising any remaining work, including support for Sightline's efforts to build and test the kernels Linaro have provided. Along with that, I would suggest a quick review of what (if anything) would be left that Sightline would want Linaro to accomplish and whether or not a contract extension is warranted to accomplish that work. Would either Tuesday or Wednesday work for you? I would expect that conversation to take no longer than 30 minutes, and I would be happy to make myself available at any time you wish. 

 

Thank you. 

 

Kind regards,

Paul

--

Image removed by sender. Linaro

Paul Neuhardt | Sr. Program Manager

T: +44 0771 377 8664
paul.neuhardt@linaro.org
IRC: pneuhardt