Hi Kim,
On 04/11/2022 17:39, Paul Neuhardt wrote:
Kim,
I had thought that the latest updates had been posted to your repository. My apologies for the misunderstanding. I will ask Dmitry to post his updates as soon as possible.
The most recent code is in the repo. I'll update the repo as soon as I have any updates from my side, including the heating fine-tuning, etc.
Paul
On Fri, 4 Nov 2022 at 14:31, Kim Steiner <kim.steiner@sightlineapplications.com mailto:kim.steiner@sightlineapplications.com> wrote:
Hi Paul,____ __ __ 1. In an email to Dmitry on 11/2/2022, I informed him that the gpu temp issue may not be fixed. He stated “Thank you for the test. I'll work on improving the warming of the CPU/GPU then.”____ __ __ 2. We still have a very slow boot up time (+2minutes).____ __ __ 3. I informed Dmitry that the glxgears application only runs for a few minutes before stopping.____ __ __ __ __ As of Wednesday (with latest git repository changes), the above issues existed and I do not plan on doing any more testing until I see new changes or get something new to test.____ __ __ I will inform Penguin Solutions that you are close so they can work on patches for us to apply to our custom board build.____ __ __ I would also like to again request a clear set of build instructions (changes to .config, compiler, initram…) so that I can build/test correctly.____ __ __ Thanks,____ Kim____ __ __ *From:* Paul Neuhardt <paul.neuhardt@linaro.org <mailto:paul.neuhardt@linaro.org>> *Sent:* Friday, November 4, 2022 7:05 AM *To:* sightlineapplications@lists.linaro.org <mailto:sightlineapplications@lists.linaro.org> *Subject:* [Sightlineapplications] Project Status and Burn Report____ __ __ All,____ __ __ Dmitry has now delivered what he believes to be the final set of updates to Sightline in support of this project. Sightline is in the process of testing these deliverables and we expect that the results will be at or close to what was expected. If there are still gaps, we will of course work to close them.____ __ __ As of today, there are still 13.5 hours of Dmitry's time left available under the most recent contract extension. This should provide adequate time for any consultation needed and any updates and/or final tuning necessary. I have attached a brief report on that burn to this email. Steve, I will send you a more detailed version that you can share inside Sightline as needed. ____ __ __ Please let me know if you have any questions or concerns. ____ __ __ While I will continue to be in touch as we close down the project, I want to take this opportunity to thank everyone involved for all their work. I am confident I speak for all of us at Linaro when I say I hope we have the opportunity to work with Sightline Applications again in the future.____ __ __ Kind regards,____ Paul____ -- ____ Linaro <http://www.linaro.org/>____ *Paul Neuhardt*|/Sr. Program Manager/____ T: +44 0771 377 8664 paul.neuhardt@linaro.org <mailto:glen.valante@linaro.org> IRC: pneuhardt____ __ __
Sightlineapplications mailing list -- sightlineapplications@lists.linaro.org To unsubscribe send an email to sightlineapplications-leave@lists.linaro.org