All,
As of the end of the day yesterday, Dmitry was still working on closed-loop handling for GFX CPR. He has spent just over a full day on that task since the last update.
At this point, we have exhausted the first tranche of 80 engineering hours and are 2-3 hours into the second. Project management time is at 7.5 hours of the 8 in the first tranche.
Updates will continue in my absence next week, most likely directly from Dmitry. I will be checking emails from time to time, so if there are any questions or concerns, please let me know.
Thanks.
Paul