All,
As of Friday, 23 September 2022, Dmitry has begun the work required in the CPU regulators. Once that work is done, he will integrate that work with the CPR work already completed. He estimates roughly 4 engineering-days of effort are required to complete that work and turn the images over for Sightline testing.
As he mentioned last week, Dmitry is out of the office this week. He will resume work on his return next Monday.
I would recommend a check-in meeting for the following week to assess the work done to that point, the testing required to validate the work done, and to start discussion around how to complete and ramp-down the project. Would Tuesday, 18 October work for everyone?
Thanks.
Paul
Hi Paul,
I did not receive an email from Dmitry last week. Can you forward it? Did he respond about the two minute boot time?
A meeting on the 18th of October would be good.
Thanks, Kim
From: Paul Neuhardt paul.neuhardt@linaro.org Sent: Monday, September 26, 2022 12:40 PM To: sightlineapplications@lists.linaro.org Subject: [Sightlineapplications] Project Status
All,
As of Friday, 23 September 2022, Dmitry has begun the work required in the CPU regulators. Once that work is done, he will integrate that work with the CPR work already completed. He estimates roughly 4 engineering-days of effort are required to complete that work and turn the images over for Sightline testing.
As he mentioned last week, Dmitry is out of the office this week. He will resume work on his return next Monday.
I would recommend a check-in meeting for the following week to assess the work done to that point, the testing required to validate the work done, and to start discussion around how to complete and ramp-down the project. Would Tuesday, 18 October work for everyone?
Thanks.
Paul -- [Image removed by sender. Linaro]http://www.linaro.org/ Paul Neuhardt | Sr. Program Manager T: +44 0771 377 8664 paul.neuhardt@linaro.orgmailto:glen.valante@linaro.org IRC: pneuhardt
sightlineapplications@lists.linaro.org