Postmortem and lessons learned for Linaro's release 2013.03
https://wiki.linaro.org/Cycles/1303/Release/Review
Highlights and Key Successes ============================ http://www.linaro.org/downloads/1303
http://wiki.linaro.org/Cycles/1303/Release#Release_Information
Blueprints ========= The number of high or essential priority blueprints that missed the cycle: Android 4 out of 12 Developer Platform 4 out of 5 Infrastructure 1 out of 5 Lava 4 out of 7 Total 13 out of 29
45% of high or essential priority blueprints scheduled for this cycle were not delivered.
Total blueprints: 22 out of 45 missed the cycle. * Not included is data from the QA team
High priority missed blueprints recap: 12.05: 19 out of 48, 39% 12.06: 13 out of 31, 42% 12.07: 14 out of 31, 45% 12.08: 6 out of 26, 23% 12.09: 9 out of 28, 32% 12.10: 15 out of 38, 39% 12.11: 7 out of 19, 37% 12.12: not available 13.01: 9 out of 28, 33% 13.02: 35 out of 69, 48%
* Not included is data from working groups and landing teams
Source: https://docs.google.com/spreadsheet/ccc?key=0AjEaTwrvj1bidExFWUpKTm1iOURjdkd...
-- David Zinman, Project Manager Linaro.org | Open source software for ARM SoCs