On Wed, Jun 13, 2012 at 8:51 PM, David Zinman david.zinman@linaro.org wrote:
Regretfully this summary is very late.
The Linaro 12.05 delivery cycle was fast and furious with Connect Q2.12, end of quarter and delivery all occurring in the same week.
During this 2012.05 Linaro Connect, much of the effort was focused on: * ARM big.LITTLE implementation and testing * Performance improvements * Linaro-linux baseline * Release process streamlining
Delivery highlights can be seen at http://www.linaro.org/downloads/1205#tab1
Platform Blueprints
The number of blueprints that missed the cycle: Android 18 out of 30 Developer Platform 6 out of 18 Infrastructure 5 out of 10 Lava 5 out of 18
Here, I am currently not sure what to do with those numbers. Basically, I am not so much worried about low/medium blueprints that didn't get delivered. Any way we could get those numbers broken down by priority? Or just a view on our delivery rates for essential and high blueprints?