On 13 June 2012 21:51, David Zinman wrote:
Regretfully this summary is very late.
The Linaro 12.05 delivery cycle was fast and furious with Connect Q2.12, end of quarter and delivery all occurring in the same week.
During this 2012.05 Linaro Connect, much of the effort was focused on: * ARM big.LITTLE implementation and testing * Performance improvements * Linaro-linux baseline * Release process streamlining
Delivery highlights can be seen at http://www.linaro.org/downloads/1205#tab1
Platform Blueprints
The number of blueprints that missed the cycle: Android 18 out of 30 Developer Platform 6 out of 18 Infrastructure 5 out of 10 Lava 5 out of 18
We're committed to deliver only essential and high blueprints. Medium and Low blueprints are over-planning and nice to have. Wrt LAVA stats, it should be 1 out of 6 .
Total: 34 out of 76 45% of blueprints scheduled for this cycle were not delivered.
- Not included is data from working groups and landing teams