The weekly report for the Linaro Infrastructure team may be found at:- Status report: https://wiki.linaro.org/Platform/Infrastructure/Status/2010-11-18 Burndown chart:http://people.canonical.com/~pitti/workitems/maverick/linaro-infrastructure....
The Infrastructure related blueprints, of which currently there are 4 active ones (4 from the last report), are showing that there are 8 work items in progress (11 last report), and 11 work items to undertake (12 last report).
arm-m-validation-dashboard; 0 work items completed since last report; 3 in progress; 7 to do arm-m-image-building-console; 1 work items completed since last report; 3 in progress; 3 to do arm-m-automated-testing-framework; no change in status from last report; 1 in progress; 0 to do arm-m-testsuites-and-profilers; no change in status from last report; 1 in progress; 1 to do
The focus for the team in the past week has remained on preparing Blueprints for the next cycle and holding the review conference call on Monday (2010-11-15).
The team had two new members join this week.
Specifics accomplished this week include:-
* A number of new PPAs were produced this week, including an improved linaro-json package and a stable API for working with dashboard bundles. * Work started on ImproveLinaroMediaCreate * Two bugs were fixed for Linaro Image Tools covering apt-get running in rootfs and replacing "sfdisk -l"with "fdisk -l" to give more useful information.
Please let me know if you have any comments or questions.
Kind Regards,
Ian
On 18 Nov 2010, at 11:46, Ian Smith wrote:
All,
The weekly report for the Linaro Infrastructure team may be found at:- Status report: https://wiki.linaro.org/Platform/Infrastructure/Status/2010-11-18 Burndown chart:http://people.canonical.com/~pitti/workitems/maverick/linaro-infrastructure....
This is the burndown chart from last cycle and has been static for quite some time. New burndown charts are yet to be set up.
The Infrastructure related blueprints, of which currently there are 4 active ones (4 from the last report), are showing that there are 8 work items in progress (11 last report), and 11 work items to undertake (12 last report).
arm-m-validation-dashboard; 0 work items completed since last report; 3 in progress; 7 to do arm-m-image-building-console; 1 work items completed since last report; 3 in progress; 3 to do arm-m-automated-testing-framework; no change in status from last report; 1 in progress; 0 to do arm-m-testsuites-and-profilers; no change in status from last report; 1 in progress; 1 to do
Will these be moved to the n-series to be re-tracked this cycle?
The focus for the team in the past week has remained on preparing Blueprints for the next cycle and holding the review conference call on Monday (2010-11-15).
The team had two new members join this week.
Specifics accomplished this week include:-
- A number of new PPAs were produced this week, including an improved linaro-json package and a stable API for working with dashboard bundles.
- Work started on ImproveLinaroMediaCreate
- Two bugs were fixed for Linaro Image Tools covering apt-get running in rootfs and replacing "sfdisk -l"with "fdisk -l" to give more useful information.
Neither of these changes have landed and are currently waiting approval to be merged.
Please let me know if you have any comments or questions.
Kind Regards,
Ian