Here's the weekly status report from the Infrastructure team. Enjoy!
You can read it in its formatted glory at
https://wiki.linaro.org/Platform/Infrastructure/Status/2011-02-10
Thanks,
James
* Period: (20110203-20110209) * PM: None * Past reports : https://wiki.linaro.org/Platform/Infrastructure * Burndown information : http://status.linaro.org/linaro-infrastructure.html * Stakeholders process: https://wiki.linaro.org/Platform/Infrastructure/CurrentProjects
== Key Points for wider discussion == * None this week
== Team Highlights == * First iteration of https://android-build.linaro.org is up and running. * First prototype of https://wiki.linaro.org/Platform/Android/Specs/AndroidMirrorService coded. * Wrote design and implementation plans for PatchTracking. * Got series support in status.linaro.org deployed. * Mattias is making progress with IT issues within ST-E. * 3/5 of the team is booked for Budapest. * Stakeholders meeting prioritized some new requests for working on soon. * Assisted with getting a hwpack for the s5pv310 set up. It is now building daily and the Landing Team can improve it. http://snapshots.linaro.org/11.05-daily/linaro-hwpacks/lt-s5pv310/ * Two weeks of facilitating the co-ordination with IS has led to as many tickets being completed by them as the previous two months.
== Upcoming Deliverables == * status.linaro.org delivered to satisfaction of interested parties within the next week.
== Risks / Issues == * Mattias unable to work productively due to IT restrictions in ST-E (2 weeks, v. high): some progress. Has process now to request changes, but not all have been acted on yet. * Mattias lacking a board to work with (2 weeks, medium): some progress, but proposed board is private currently, and is apparently wanted for use by several people. Mattias will work on a project that doesn't require a board in the meantime. * Deepti lacking a board to work with (many weeks, high): A Panda board is earmarked, but Deepti has not yet received it. Working on tasks that don't require it, but unable to participate in image testing. * PatchTracking requires deploying Patchwork (0 weeks, high): Co-ordination of this will start with IS immediately. * Patchwork seems unmaintained upstream (0 weeks, low): Will monitor. Can always use a fork for our purposes. * Gerrit instance needed for Android (0 weeks, high): Co-ordination with IS has started. Waiting to hear from them if we can get it this month, and what we need to do to help with that. * OurOwnOffspring lacking hardware (many weeks, medium): x86 for master is ready and waiting, Joey has ordered XMs for slaves, should be here this month. * Want a Hudson instance for Continuous Integration purposes (many weeks, medium): Discussions with IS, and they will provide one, but timeframe is unclear at this point. Will host ourselves until IS can provide. * No project manager for the team (0 weeks, high): Joey is working to solve. James will do these duties for the team in the meantime.
== Miscellaneous == * Deepti spent 1 day at IBM internal meeting this week. * Guilherme on vacation this Friday. * James on vacation 17th-22nd February. * Multiple absences planned for March.