The weekly report for the Linaro Infrastructure team may be found at:- Status report: https://wiki.linaro.org/Platform/Infrastructure/Status/2010-12-09 Burndown chart: This link is awaiting the production of new burndown charts.
The Infrastructure related blueprints from the maverick cycle, of which currently there are 4 active ones (4 from the last report), are showing that there are 8 work items in progress (8 last report), and 11 work items to undertake (11 last report). These are to be moved into the natty cycle if still required.
* arm-m-validation-dashboard; no change in status from last report; 3 in progress; 7 to do * arm-m-image-building-console; no change in status from last report; 3 in progress; 3 to do * arm-m-automated-testing-framework; no change in status from last report; 1 in progress; 0 to do * arm-m-testsuites-and-profilers; no change in status from last report; 1 in progress; 1 to do
In the natty cycle, the following lists the current active Blueprints, or Blueprints planned and not started. Currently there are 4 active Blueprints (4 from the last report), which are showing that there are 8 work items in progress (7 last report), 41 work items to undertake (46 last report), 2 work items postponed (0 last report) and 8 work items added (all items added last report).
* other-linaro-n-improve-linaro-media-create: 5 work items completed (2 last week); 4 work items in progress (3 last week); 8 work items to do (8 last week); 2 work items added this week (2 last week). * other-linaro-n-test-result-display-in-launch-control: 0 work items completed (8 last week); 1 work item in progress (1 last week); 10 work items to do (10 last week); 0 work items added (4 last week) * other-linaro-n-patch-tracking: 0 work item completed (0 last week); 2 work items in progress (2 last week); 9 work items to do (9 last week) * other-linaro-n-image-building: 2 work items in progress (2 last week); 5 work items to do (5 last week); 2 work items postponed (2 last week); 0 work items added (2 last week) * other-linaro-n-continuous-integration: Not started - awaiting a Hudson build server (RT#42278). * other-linaro-n-package-development-tools: Not Started; 9 work items to do
Specifics accomplished this week include:-
* other-linaro-n-image-building: "4.6 Multiple hwpacks": basically done - needing test and review. * ImproveLinaroMediaCreate: completed the ports to Python of "populate_boot" and "create_partitions" - waiting for review on "create partitions" * Added blueprint/bug links to the LaunchPad API. This is now landed and tested. * Also finished porting the work items tracker to use the launchpad APIPlease let me know if you have any comments or questions.
Kind Regards,
Ian
On 10 Dec 2010, at 13:56, Ian Smith wrote:
- Also finished porting the work items tracker to use the launchpad
APIPlease let me know if you have any comments or questions.
Just to make it clear, this work has not been completed and is still in progress. Currently no code changes have landed to the work items tracker but James is doing a stella job trying to investigate fixes.
Kind Regards,
Ian
Regards, Jamie. -- Linaro Release Manager