This is just an early notification that the Linaro validation farm will be physically moving to a new site next week. Unfortunately, the network cables won't stretch that far, so it will mean some downtime. :)
Here's the tentative plan:
Wednesday, March 21st - the rack with the toolchain server will be shut down, crated and sent off Thursday, March 22nd - pretty much everything else will go offline (main LAVA server, development boards) Friday, March 23rd - physical move will happen, and if all goes well (what could possibly go wrong?!) the main site and as many of the boards as possible will go back online in their new home Saturday, March 24th to Sunday, March 25th - finish configuring and bringing up cloud services, toolchain server, etc.
There's another bit of good news here, that the lab will be getting a much needed upgrade in the internet connection. A partial (but significant one) at first, and a bigger one in about a month or so with redundant connections.
Bear in mind that this is just the tentative plan, Dave or I will send out a reminder and update as the date gets closer, or if something changes.
Thanks, Paul Larson
On 16 March 2012 15:50, Paul Larson paul.larson@linaro.org wrote:
This is just an early notification that the Linaro validation farm will be physically moving to a new site next week. Unfortunately, the network cables won't stretch that far, so it will mean some downtime. :)
Here's the tentative plan:
Wednesday, March 21st - the rack with the toolchain server will be shut down, crated and sent off Thursday, March 22nd - pretty much everything else will go offline (main LAVA server, development boards)
I'll pause the tcpanda boards on Tuesday and shut them down on Wednesday. Our release is done so this should be fine.
-- Michael
Just a reminder to everyone that I will start decommissioning the toolchain server and lava cloud tomorrow morning, and then LAVA will go offline on Thursday morning. If all goes according to plan then a limited LAVA service should be available late on Friday, and I will work across the weekend to get everything else back up and online.
We will be doing our best to keep the downtime to an absolute minimum, but the best laid plans can go awry. The major part that would push the availability out would be if our ISP do not keep to their commitment to get us connectivity by Friday. I will keep you informed as to progress during the move as and when possible.
Many thanks for your patience,
Dave
Dave Pigott Validation Engineer T: +44 1223 45 00 24 | M +44 7940 45 93 44 Linaro.org │ Open source software for ARM SoCs Follow Linaro: Facebook | Twitter | Blog
On 16 Mar 2012, at 02:50, Paul Larson wrote:
This is just an early notification that the Linaro validation farm will be physically moving to a new site next week. Unfortunately, the network cables won't stretch that far, so it will mean some downtime. :)
Here's the tentative plan:
Wednesday, March 21st - the rack with the toolchain server will be shut down, crated and sent off Thursday, March 22nd - pretty much everything else will go offline (main LAVA server, development boards) Friday, March 23rd - physical move will happen, and if all goes well (what could possibly go wrong?!) the main site and as many of the boards as possible will go back online in their new home Saturday, March 24th to Sunday, March 25th - finish configuring and bringing up cloud services, toolchain server, etc.
There's another bit of good news here, that the lab will be getting a much needed upgrade in the internet connection. A partial (but significant one) at first, and a bigger one in about a month or so with redundant connections.
Bear in mind that this is just the tentative plan, Dave or I will send out a reminder and update as the date gets closer, or if something changes.
Thanks, Paul Larson
linaro-dev mailing list linaro-dev@lists.linaro.org http://lists.linaro.org/mailman/listinfo/linaro-dev